Estimated Timeline for MDM Migrations using Jamf Migrate

Jamf Migrate for macOS User Guide

Solution
Application
Content Type
Technical Documentation
Utilities & Services
Jamf Migrate
ft:locale
en-US

The time necessary to migrate all your computers to Jamf Pro is not dependent on the amount of computers in your environment, but rather the complexity of your environment and the effectiveness of your migration communications.

Jamf recommends phasing your migration over a period of 4-8 weeks. A deployment plan might look similar to the following:

Week 1: Planning and communication. Week 2: User-initiated migration phase. Week 3: Enforced migration phase.